Hi Experts,

I have a question regarding document flow. I used a BOM in Quotation (Higher Level Item Category - TAQ, Sub Level Item Category - TANN) with quantity 2.

I created 2 Sales Orders (OR) with 1 quantity each. When I check the document flow, the Quotation has status "Being Processed".

Document Flow: -

Quotation 0020000039 Being processed

Standard Order 0001020265 Being processed

Standard Order 0001020266 Being processed

When I click on Quotation and say Status Overview, the following is displayed.

Total processing Being processed

Delivery status Not delivered

Completeness Complete item data

Confirmation status All items confirmed

Rejection status Nothing rejected

Reference status Fully referenced

Delivery complete Complete item data

Billg doc. complete Complete item data

The following configuration is done: -

Item Category TAQ Definition - Completion Rule set to "B"

Copy Control - QT to OR - for TAQ, update document flow is "Checked" and Pos./neg. quantity is "+"

My Question: -

Why Quotation is having the status "Being Processed" not "Complete" as it is completely referenced?

The TAQ is not relevant for delivery, but TANN is relevant for delivery.

Please let me know whats happening here and what needs to be changed....

Thanks,

SAP SD Learner

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Aug 18, 2011 at 03:38 AM

    Hi,

    Please check the Cpmpletion rule in the Item category.... It will helps you.

    Regards,

    Krishna Ch

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 18, 2011 at 11:34 PM

    Hi All,

    I am able to solve this problem.

    Cause: -

    I used TAQ for BOM Higher Level Item (Item Category determination in QT) and it was assigned a Schedule Line category CT.

    Solution: -

    Create a copy of TAQ say ZTAQ and assign Schedule Line category BT to it. And then as usual carry out Item Category determination, copy control, completion rule and etc...

    Impact: -

    Now the Quotation is complete !!!!!! 😊

    Thanks,

    Red Raider

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 18, 2011 at 11:41 PM

    ...

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.