Report S_ALR_87013532- problem

Former Member
0 Kudos

Dear Experts ,

Earlier i had a problem that production order cost were not picking in cost element report S_ALR_87013542 report. Through sdn forum i found out OPSV configuration were mising for Production orders. I made the configuration and it worked.

But now again i am facing a similar kind of problem with Plan/Actual variance report S_ALR_87013532.

Although labour cost is getting picked from order against WBS , but material cost is not picking up from orders to WBS.

In my viw the same OPSV configuration should work for this report also. But this is not happening.

Need expert opinion on this matter.

Thanks ,

Vishal

Accepted Solutions (1)

Accepted Solutions (1)

former_member230675
Active Contributor
0 Kudos

please reconstruct logical data base (CJEN) and check the report again.

while reconstructing data base system will show warning message if the value categories are not maintained properly, then please maintain value category as well.

Former Member
0 Kudos

Dear All,

Thanks for the reply.

I had run CJEN for the concerned project , but still material plan cost is not picking up for orders against WBS in S_ALR_87013532 report.

Also I am not getting any message for maintaining values categories while executing CJEN .

I have not been able to find the root cause of this problem .

Kindly suggest.

Thanks,

Vishal

Former Member
0 Kudos

Hi,

Are those values displayed in other standard reports? If not, then check the alue category assignmnets for the cost element for material cost planning. If yes, then check the profile settings for this report and also check for any filters / exclusions.

Regards

Sreekanth

former_member230675
Active Contributor
0 Kudos

may be, you can check whether you have created statistical cost element for your material inventory account or not, if not please create one and try.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Vishal,

Are you using non valuated project stock and then have production orders assigned to WBS Element?

If that is the case, only labour costs will be shown for production order and material costs does not move from WBS to production order after GI to prod ord

BR / Parimal

Former Member
0 Kudos

Dear All,

Thanks for suggestions.

I have checked the suggestions , but it is not working.

I have also checked other reports like s_alr_8701342/43 where plan cost of material is coming properly against wbs/project.

I have noticed one point in the output message, while we execute CJEN for the concerned project .

I think this has some connection with material plan cost.

Object , Value Category , Value type , Obj. Indicator

ORD 60000669 , Labour , 1 , 1- Order plan values: appended, apportioned

ORD 60000669 , Material , 1 , 3- Order plan values: appended, not apportioned

I found that component (materail) always appears with obj indicator 3 for all orders.

I also understand that object values with Object indicator 3 does not get added in plan value of the WBS .

I dont know the root cause , why the material plan values appear with object indicator 3. Is there any config missing.

One more important point on this matter not shared by mistake.

The cost is not flowing from objects to WBS level in S_ALR_87013532 report.

Kindly suggest .

Thanks ,

Vishal

Former Member
0 Kudos

Dear All ,

I am closing this thread.

I think some basic configuration in planning profile & costing is misiing . Need to explore & find the solution.

Thanks all for your suggestions & help.

Regards,

Vishal

Former Member
0 Kudos

Hi,

Please check the below link...

Kuber