Hello,

I'm hoping someone can advise what we need to do as two of our main contracts appeared to have 'locked up' and gone into a held status. We are currently using CCM SRM 5.0.

When going into change the contracts, the release button is greyed out and the error message we receive is 'No purchasing group exists'. However, the contracts do have a valid purchasing group assigned.

At the time they went into a held status we were trying to add items/remove items etc for one and re-activate an item on the other.

Since they have gone into a held status, changes have been made to other contracts successfully, but no-one is able to bring these contracts out of the held status.

Any suggestions on what we can do would be greatly appreciated.

Many Thanks

Lisa

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

This is due to change version exists in Contract. To cross check please have a look on BBP_PD with appropriate contract object type. You have to close the change version by putting X mark against document closed in the table BBP_PDHGP or

try with selecting DELETE button from the Process Contract screen. It will ask popup for you to accept that change version will be deleted. Please accept so that the contract will be automatically changed to RELEASED. I hope the above information is very useful to you.

Thanks

Rajesh K

lisa_pallas
Explorer
0 Kudos

Many Thanks Rajesh, your solution has resolved my problem. Lisa