on 08-11-2011 6:46 AM
Dear Sir
I have a query, The scenario is different workcenters for all different work cetenters cost center is the same and activities is
also the same.Cleint wants the cost calculation as per the cost of the machine as per usage and they have a different rates in similar workcenters ? How can I get the different rates in same costcenter and same activity types.
Please help me Its urgent!!!
Shiv
Dear Shiv,
Normally a work center can be assigned to only once cost center. At a cost center for the same activity we will have only one rate. By this way it is not possible to have different rates for the same activity and cost center.
You can create different Activity types and mantian the rates accordingly.
Also, you can check with your PP consultant if it can be manged using control key in the routing.
Kind Regards
Umapathi G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Siva
This is useful link for query
http://www.sapsword.com/home/learn-sap-pp/sap-workcenter
Regards
Vinod
Edited by: Vinodkumark on Aug 11, 2011 2:13 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.