Skip to Content

Schedule Line Category.....

Hi Experts,

I am working on a 3rd Party scenario where client do not want to have NB doc type for PR instead they have a customized doc type as ZZ which they want us to maintain in the schedule line cat...

Besides the 3rd party scenario here we follow is quite different means at schedule line cat level we have 601 mov type and Pur req del scheduling is also checked so that in the system we receive goods and do PGI but physically its been delivered by Vendor this is what I understood by seeing the settings....

My question is after copying CS and renaming it as ZS and if I try assigning ZZ PR doc type an error msg crops up"goods movement not possible for third party schedule lines".......why is that error am facing?....

Also can anyone suggest me how to circumvent this issue?....

If its not possible then how in the std CS schedule line cat 601 mov type is maintained?......

Thanks in advance....

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Aug 09, 2011 at 12:12 PM

    Hi,

    If its not possible then how in the std CS schedule line cat 601 mov type is maintained?

    1.In standard SAP we can't Find Movement type 601 for CS Schedule Line

    2. I tried in my System , system won't accept the movement type 601 for CS if enter system will through the error "Goods movements is not possible for third-party schedule lines"

    Can you please clarify what schedule your selected

    Regards,

    Prasanna

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 09, 2011 at 11:55 AM

    Hi

    Try by changing the Item category and also maintain the necessary configuration for the new item category as per the requirement.

    Or instead copy from CB Schedule line ategory

    regards

    Prashanth

    Add comment
    10|10000 characters needed characters exceeded