We have created a Customized report for variance, trend and % of completion for the WBS elements. For % of completion we created so many version starting from 0, 0XX, etc . we have a report through which we can copy the values from version 0 to version 0XX, it shows copied successfully , but the data now in 0XX is not matching with version 0 . Wer am i missing out?
since it is a customized transaction it will be better you check with your abaper and ask him to debug and see the issue..
why don't you try the standard option CJ9BS - Copy WBS Plan to Plan (Indiv.) or CJ9FS - Copy Project Costing (Indiv.)