Hi,
I am getting a unique error in task list...
Scenario is that i have maintained general task list with work updated in it and there is no calculation key maintained in it.
Now, when i assign this task list to a Maintenance Order it shows work hours as mentioned in the task list....
But when I save it and again open the order then work hours comes as 100 irrespective of the value maintained in task list.
Now, if i assign another task list which has calculation key assigned to it then there is no problem.
Can anyone please help me on this.
Thanks & Regards,