In original Budget crossing the limit for a particular order no error procd

Hi

In budget where the amount exceeds the original budget without showing any error message for budget exceeding. for example order no:xxxx amt 100000 and posting amt 200000 without error system proceeding. But generally system don't allow if we crossing the limit for a budget. here there is no error. I have to make it to appear error. Any solution is to rectify..

Thank u

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    Posted on Aug 08, 2011 at 10:24 AM

    Dear,

    Please check if you have defined any Availability Control in OKOB.

    Please check and revert.

    Br,Vivek

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.