on 08-07-2011 6:14 AM
We are on ECS SRM 7.
Trying to create a limit SC or a PO and the contract limit is greyed out. I have tried setting the IV based and GR based flags but it doesn work.
Any suggestion?
Thanks
i think it is standard functionality.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Have a look at OSS note below:
[1358679 - Contract Limit fields enabled in extended classic scenario|https://websmp130.sap-ag.de/sap%28bD1lbiZjPTAwMQ==%29/bc/bsp/spn/sapnotes/index2.htm?numm=1358679]
If you have local contracts (i mean, not replicated to R/3 backend), it is definitely not possible.
With existing R/3 contracts, even if you modify how your source of supply (contracts) is determined, npt sure it could be possible.
I heard new business fonctions from ECC 6 EHP5 contain features for the integration between a SRM and an ERP system (Service procurement with central contracts).
Regards.
Laurent.