Total operation hours in routing

453 Views

Dear Experts,

Please suggest me what is the way to tackle the following scenario :

We are having 3 Work Centers say WC1, WC2, WC3 to carry out the different operations. Each work center requires 6 hours. It means if I use the standard sequence then total required hours will be 18 hr to produce 1000 pcs of FG X. But My client is producing 1000 pcs of FG X in 8 hours as second operation at WC2 begins when 1st operation on WC1 is being carried out on some quantity say 100 pcs. 7 same for the WC3.

How to control this situation as I am using the lead time scheduling in MRP run,this data gets coppied to planned order giving wrong finished date.

Thanks in advance.