Hi ,

in one of my scenario i created performance based strategy plans as below for every hrs. 500, 2000, 4000, 8000. when we started using sap counter reading was 16500hrs, if i entered this reading system generates "N" of orders as per the strategy performance. Now user wants system should generate the order from 17000hrs onwards only. Please suggest me. I am struck up at here, how i can proceed it? Annual estimate i given 8760hrs.

please guide me.

thanks & regards