on 08-04-2011 6:46 PM
Hi ,
I am having a issue with the CumQtyInTransit field on the scheduling agreement. This field is not adjusting the deliveries created when the new forecast comes in. What could the reasons for the issue and how can I resolve it? PLease advice
Thank you
If a cumulative quantity received by customer was sent in the IDoc in
the past and if the customer sends the IDoc without cumulative quantity
received by customer now, you need to correct the delivery schedule
manually once so that the system proposes the cumulative quantity
received by customer again as of the next IDoc.
Hope this helps
regards,
Ramana