Skip to Content
0
Former Member
Jul 29, 2011 at 06:23 AM

Getting Budget error at the time of MB1A transaction..

48 Views

Hi,

When executing transaction MB1A for goods issue against Network activity user getting budget error as

"Item 123 Network Activity xyz budget exceeded "

1.79 Crore Released budget is available in the WBS in current Fiscal Year.

And material cost is just Rs. 17 Lack.

I have checked table BPVJ1, Released budget is updated in this table still getting the budget error.

Please provide the solution.

Thanks in advnc!

Regards,

Archana