Hi,

When executing transaction MB1A for goods issue against Network activity user getting budget error as

"Item 123 Network Activity xyz budget exceeded "

1.79 Crore Released budget is available in the WBS in current Fiscal Year.

And material cost is just Rs. 17 Lack.

I have checked table BPVJ1, Released budget is updated in this table still getting the budget error.

Please provide the solution.

Thanks in advnc!

Regards,

Archana

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Check the tolerance Limit for your Budget profile.

former_member220491
Active Participant
0 Kudos

Hi Archana,

As our friends suggested all the possible senarios. I request you to kindly check also whether Person responsible is assigned to that respective WBS or not, because even through budget is allocated and released, and in your budget tolorence limit you have set option 2 that is warning with email, system will be looking for the person responsible to that wbs to send the email, if it is missing also system will throw same error that budget is exceeded.

reasons

1. Check tolorence limits

2. person responsible for the respective WBS

3. re-construct the budget availability control.

4. This is not a suggested to do but, if it is stopping your process deactivate the budget availability with tcode:CJBW and after completing your transaction you can activate it back by CJBV( note: this is not a good practice)

Thanks

regards

kishore

Former Member
0 Kudos

archana

am agree with kishore, even am suggesting for deactivation by cjbw and after passing entries you can again activate by cjbv.

or check through status management.which will help you to find the details of your budget status whether it is released or not.........

Former Member
0 Kudos

Many Thanks to all of you! And Thanks a lot Mr. Sandeep.

After executing CJBN Transaction user is now able to Post document in MB1A. Issue is resolved now.

Regards,

Archana

stheurkar
Active Contributor
0 Kudos

Hi,

Have you checked annual & overall available budget in S_ALR_87013558 report?

Regards,

Sandeep

Former Member
0 Kudos

Yes! I have checked in S_ALR_87013558 report also. Overall available budget is 1.79 Crore.

kalpesh_agrawal
Participant
0 Kudos

hi,

S_ALR_87013558 report gives budget and not budget release. Pl check if budget has been releaed or not. If yes then check whether it has been distributed to its chield WBS's or what.

Regards,

Kalpesh

Former Member
0 Kudos

Hi,

Budget is released and its distributed to child WBS . Released Budget is updated in table also.

stheurkar
Active Contributor
0 Kudos

just check report S_ALR_87013560 for current & release budget. Check amount for annual and overall.

Former Member
0 Kudos

Checked current and released budget in S_ALR_87013560 report its showing 1.79 Crore amount .

Anual and overall amount is also 1.79 Crore.

stheurkar
Active Contributor
0 Kudos

try reconstructing availability control by using CJBN & project info database by using CJEN transactions.

also share error message no what your getting.