HI,

How sales order costing should be activated.So that it will help business to know profitablility on the basis of customer/Order/Product.

Please give me the cutomization process of Sales order customization.

Thanks,

Miku.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jul 28, 2011 at 08:39 AM

    Hi,

    In standard If you assign variable price or standard price in material master in accounting tab then it will flow automatically in sales order as VPRS internal price

    Then you just put your price then at last system will calculate profit margin

    Please refer the standard pricing procedure RVAA01 and see how configure is done for VPRS and profit margin

    Now if you want to calculate cost on bais of material BOM then maintain material bom for finished product

    and in material master maintain bom usage and all other date in costing tab 1

    Also need to configure costing varient in CO

    Then create sales order for finished material then go to item level and click on costing (icon calculator)

    then put costing varient if not appearing default and enter the cost will be calcualted on basis of BOM material then save

    Now go to condition tab and see condition type EK02 is appearing and showing cost

    Kapil