how to change pr qty before mrp run is over

Former Member
0 Kudos

i have requirement where some additional pr need to added in mrp

run

any badi is available for that

or any logic

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Try with following exits :

Enhancement/ Business Add-in Description

Enhancement

LMDZU001 User exits in additional planning

LMDR2001 User exits restr. profiles of opt. pur.ord.-based load bldg

Develop any of the above enhancements with help of your technical consultant in CMOD transaction.

Regards,

Tejas

Answers (1)

Answers (1)

Former Member
0 Kudos

The query is as cryptic as it can be.

If there is an unmet demand (i.e. by stock or a supply proposal), MRP run by default will put a supply proposal i.e.a PR for a buy material.

So what is the need for a BADI for this? It would help if you clearly state what exactly is the need or the exact issue you face to obtain a meaningful response from the forum.

Former Member
0 Kudos

annually for raw material they want to add allowance say make pr with 10% additional allowance

so pr qty may rise

how to include this

Former Member
0 Kudos

For that need before looking at BADI's evaluate the below options & adopt the one which best fits

1. Add scrap % as 10 (in MM data - MRP4 view), thereby system will increase the planned qty

2. Check if you can work with rounding values / rounding profiles

3. Check if fix lot sizing with fix lots can help

Do some tests with the above options & revert if you face any specific issues.