process chains

when will be process chains scheduled while client location is uk and we are working in india what will be the best time to run process chains and what is the use to run process chains .

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Jul 25, 2011 at 12:14 PM

    Hello Kalyan,

    Its recommended to run the PCs at night time (midnight), when users are not blocking the planning area. If you have users in American continent then try to extend the timings in late GMT.

    Details regarding process chain can be found under this[ link|http://help.sap.com/saphelp_nw04/helpdata/en/8f/c08b3baaa59649e10000000a11402f/content.htm].

    Regards

    Rahul Chitte

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 24, 2011 at 09:05 PM

    Kalyan,

    1._Process chains_ are used to schedule Batch jobs. Process chains achieve the same objective as scheduling jobs in background using SM37, but with lot more flexibility when it comes to handling dependencies between jobs and its more easy to do prodution support and maintenance using Process chains.

    2. TIMING: Well the timing of the process chains depends on the type of process step/activity you are trying to run. If the step is something that cannot run when the data is locked by the user, then since you are telling your client is in UK, its better to run when the end users are not working on the system..i.e, UK night time. But if the process step/Job can be executed independent of user activity in the system, then you can schedule it anytime. The preferred approach is to schedule a chain when the system load is less OR when there is not much user activity, for example during weekends or as nightly jobs.

    Hari Vomkarey

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 11, 2012 at 05:30 AM

    Standard Procedure for Triggering the Process chains are through Back Ground process(Scheduled). It depends on which extractor do you want to extract the DATA either Standard LO or Generic or COPA extractor. In case of the LO the Deltas can scheduled based on the back ground job and see whether USER doesnt LOCK the DATA( Especially during the off peak times the DATA are Loaded). Generic you can extract at any time(Suggested that u extract during the Off Peak Hours).

    Add comment
    10|10000 characters needed characters exceeded