Hi,

I am trying to create a new user status for a WBS in OKO2 which will forbid material postings through requisitions and orders and also forbid sales orders to be created. These are standard business transactions and I can see are easily available to forbid when creating the new status.

It works when trying to create a new material document or sales order.

However, can anyone help as I am also trying to ensure that if a material posting has been made already to the WBS or sales order is assigned and then someone tries to change the user status to this new user status, then the validation of the project on save will create an error message an advise that the status can not be set due to an existing material document or sales order.

I would like to do this without having to create an additional validation user exit.

Can anyone advise if this is possible?

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

For postings that are already made this can't be achieved. As suggested by Abdul you may have to use Validations or any other work around to achieve this.

Former Member
0 Kudos

Thank you both. I thought this may be the case

former_member230675
Active Contributor
0 Kudos

I do not think you can achieve this without a validation..