Cost work center A to work center B

Former Member
0 Kudos

Dear All,

I must to modeling this situation:

I created an production order. In routing I used an work center A.

After I confirmed a half of quantity, I want to transfer the cost the work center A to and other work center B.

I want to keep the history u2018s confirmations on the work center A.

The first confirmation CO11N on the order 1 and work center A => Quantity 1 hrs.

Actually we transfer the cost by KB15N by at the level EOTP.

We want to push the cost down at the work center.

So we want this situation :

The first confirmation CO11N on the order 1 and work center A => Quantity 1 hrs.

The second confirmation on the order 1 and work center A=> Qauntity -1 hrs ( Itu2019s possible and how?)

The third confirmation CO11N on the order 2 and work center 2 => Quantity 1 hrs.

Thank you for your answer.

Regards,

Géraldine

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello,

The user clock in his time by CO11N, for example 2 hrs, on the posting date 2011.02.01 (on the project A).

After the cost transfer into CO.

At the end of the project, on the posting date 2011.06.01 , we want to transfer 1 hrs and the cost to an other project B.

I try two incorrects solutions :

- The first : I can't use the CAT5 by negative value.

- The second : The user don't want to modify or cancel the initial confirmation.

How can i to deduct one hour from the initial project to the second project, and i want to keep the information work center ?

Can you help me ?

madlercm
Active Contributor
0 Kudos

Costs are not managed on work center level, but on the cost center to which they are linked. So, your case is not really clear to me.