Hi Experts,

is it advisable to create an own Factory Calendar for PM with 7 work days. If i would like to book a confirmation on a saturday, i will get a w-message, because this day is not a work day in the Standard Factory Calender. Are there any points i have to be careful or is this no problem to create a own calender for all PM Work Centers?

Thanks & BR

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jul 21, 2011 at 01:39 PM

    Hi,

    You can create your own Factory Calendar for Plant Maintenance. Assign the same in Work Center. Even in Maintenance Strategy, you can go with Factory Calendar based package. So that, It will create as per the PM Factory Calendar.

    Regards,

    Maheswaran.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.