on 07-21-2011 12:11 PM
Hi
I have followed the below steps but still the Schedule lines is not generated for scheduling agreement.
1Maintain MRP views 1,2,3,4 for the material in material mste.(MM01)
2. Maintain Purchase Info Record for the vendor plant & material combination.(ME11)
3. Create Scheduling agreement using ME31L
4. Maintain source list for the material & the scheduling agreement # and Line item set the MRP relevant indicator 2 (Necessary ?) ME01
During Run MRP for the material.the below details entered///
Processing key NETCH Net Change in Total Horizon
Create purchase req. 1 Purchase requisitions in opening period
Schedule lines 3 Schedule lines
Create MRP list 1 MRP list
Planning mode 1 Determination of Basic Dates for Planned
Run MDBT or MD02 but still doesn't create the schedule lines......Anything else missing.
MRP1:
MRP Procedure: PD
MRP Group: 0000 (External Procurement only)
Lot Size: EX (Lot For Lot)
MRP2:
Procurement Type: F
Sched Margin Key: 000
MRP3:
Avilablity chec: 02 (Individual requirement)
MRP: 4
Nil
Raj,
Source List a Mandatory for Scheduling Agreement, if you want to create automatic Scheduling line.
Plz use (2) in MRP RELEVENT tab in ME01 (Source List).
rest of the thing is ok, make sure a material master(MRP 2 VIEW) in that view you have to give a planed delivery days. it is must.
HOPE IT WILL WORK
Regards:
Poision
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.