multiple assetcode in p.o

Dear Cons

In a P.O there is only one line item.the account assignment is A.(ASSET).The qty. is 10. In accountasignment tab of PO we select distribution field as quantity basis & entered multiple asset code.But after entering we saw the GR NON VALUATED IS ACTIVATED IN DELIVERY TAB.why it is happening . is there any impact happen in asset regester at the time of GRN asit is valuated at GRN.PL HELP.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jul 21, 2011 at 07:54 AM

    Hi,

    It was standard until ECC 6.0 Ehp 4.

    You need to activate business function LOG_MM_MAA_1 in SFW5 to allow valuated multi account assignment.

    Regards

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 21, 2011 at 07:49 AM

    Its a std SAP functionality to enable the GR non valuated for multiple account assignments. GR will be non valuated in this case.

    [http://help.sap.com/saphelp_46c/helpdata/en/75/ee0e0355c811d189900000e8322d00/content.htm]

    Edited by: Karthik on Jul 21, 2011 3:50 PM

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.