Dear Gurus,

I am creating a project with 6 WBS elements. When I am creating internal activity then my control key is PS01.

My requiremenet is that only for 1st WBS of every project, my internal activity should be ZPS1 and for remaining it would be PS01. Is it possible through substitution ?

Please guide

Keshav

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Jul 20, 2011 at 10:24 AM

    Dear Gurus,

    please reply

    Keshav

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      Identify a unique number for this one activity (this may have to be part of process) and then use this activity number as reference for the substitution.

      Regards

      Sreekanth

  • avatar image
    Former Member
    Jul 21, 2011 at 05:42 AM

    Dear Sreekanth,

    That is not only for a particular project. Its for all the projects that 1st WBS should have internal activity with control key as ZPS1 and for remaining it should be PS01.

    Regards

    Keshav

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 21, 2011 at 06:34 AM

    Hi,

    SPRO >> PS >> Structures >> Operative Structures >> Work Breakdown Structure (WBS) >> Define Field Selection for Work Breakdown Structures >> Field Selection: WBS Element >> F2

    Here define the 6 levels of WBS as per your requirement.

    And in substitution, try to add control Key as fixed value for WBS level 1.

    I am not sure it will work, but have a try

    Regds,

    CB

    Add comment