on 07-20-2011 7:35 AM
Dear Gurus,
I am creating a project with 6 WBS elements. When I am creating internal activity then my control key is PS01.
My requiremenet is that only for 1st WBS of every project, my internal activity should be ZPS1 and for remaining it would be PS01. Is it possible through substitution ?
Please guide
Keshav
Hi,
SPRO >> PS >> Structures >> Operative Structures >> Work Breakdown Structure (WBS) >> Define Field Selection for Work Breakdown Structures >> Field Selection: WBS Element >> F2
Here define the 6 levels of WBS as per your requirement.
And in substitution, try to add control Key as fixed value for WBS level 1.
I am not sure it will work, but have a try
Regds,
CB
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sreekanth,
That is not only for a particular project. Its for all the projects that 1st WBS should have internal activity with control key as ZPS1 and for remaining it should be PS01.
Regards
Keshav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Gurus,
please reply
Keshav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.