on 07-20-2011 7:09 AM
Hi SD Experts,
I have a requirement that , the planned GI date in delivery document should push to the dates depends upon the route transit days selected in the sales order.
For example
I have 2 routes say ZAPP1 and ZAPP2 which has transit period 2 days and 3 days. In sales order , if i select ZAPP1 then the planned GI date in delivery docuemnt should push to 2 days.
Now, the system scheduling the delievery according to the route selected , but in delivery docuement Plnd GI remains the same date.
Looking forward for your valuable suggestion.
Thanks in Advance.
Thanks and Regards
Praveen S
Hi
Goto your delivery doc type settings and select option 'y' in rescheduling.
If the indicator is set to 'Y' deadlines are redetermined even if there is a change in the routes that were transferred from the order, or if a new route plan is determined.
Hope this helps.
Regards
Madhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Praveen
Maintain Loading Time w.Days & Pick/pack time wrkdys in shipping point (Enterprise structure - definition-Logistics execution - define shipping point) . Route is determined based on shipping point so according to your shipping point system will confirm the schedule line for that day and delivery takes place according to that.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.