Planned G I date in deleivery docuement

Hi SD Experts,

I have a requirement that , the planned GI date in delivery document should push to the dates depends upon the route transit days selected in the sales order.

For example

I have 2 routes say ZAPP1 and ZAPP2 which has transit period 2 days and 3 days. In sales order , if i select ZAPP1 then the planned GI date in delivery docuemnt should push to 2 days.

Now, the system scheduling the delievery according to the route selected , but in delivery docuement Plnd GI remains the same date.

Looking forward for your valuable suggestion.

Thanks in Advance.

Thanks and Regards

Praveen S

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jul 20, 2011 at 06:45 AM

    Hi Praveen

    Maintain Loading Time w.Days & Pick/pack time wrkdys in shipping point (Enterprise structure - definition-Logistics execution - define shipping point) . Route is determined based on shipping point so according to your shipping point system will confirm the schedule line for that day and delivery takes place according to that.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Vinayak ,

      Thanks for Replying ,

      Delivery Scheduling is happening according to Route Transit time, But i need achieve as follow, the Planned Good Issue date in Delivery docuement should change depend upon the Route selected in sales order.

      Thanks and Regards

      Praveen S

  • author's profile photo Former Member
    Former Member
    Posted on Jul 20, 2011 at 06:54 AM

    Hi

    Goto your delivery doc type settings and select option 'y' in rescheduling.

    If the indicator is set to 'Y' deadlines are redetermined even if there is a change in the routes that were transferred from the order, or if a new route plan is determined.

    Hope this helps.

    Regards

    Madhu

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.