Planned G I date in deleivery docuement

Former Member
0 Kudos

Hi SD Experts,

I have a requirement that , the planned GI date in delivery document should push to the dates depends upon the route transit days selected in the sales order.

For example

I have 2 routes say ZAPP1 and ZAPP2 which has transit period 2 days and 3 days. In sales order , if i select ZAPP1 then the planned GI date in delivery docuemnt should push to 2 days.

Now, the system scheduling the delievery according to the route selected , but in delivery docuement Plnd GI remains the same date.

Looking forward for your valuable suggestion.

Thanks in Advance.

Thanks and Regards

Praveen S

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

Goto your delivery doc type settings and select option 'y' in rescheduling.

If the indicator is set to 'Y' deadlines are redetermined even if there is a change in the routes that were transferred from the order, or if a new route plan is determined.

Hope this helps.

Regards

Madhu

Former Member
0 Kudos

Hi Praveen

Maintain Loading Time w.Days & Pick/pack time wrkdys in shipping point (Enterprise structure - definition-Logistics execution - define shipping point) . Route is determined based on shipping point so according to your shipping point system will confirm the schedule line for that day and delivery takes place according to that.

Former Member
0 Kudos

Hi Vinayak ,

Thanks for Replying ,

Delivery Scheduling is happening according to Route Transit time, But i need achieve as follow, the Planned Good Issue date in Delivery docuement should change depend upon the Route selected in sales order.

Thanks and Regards

Praveen S