I am creating PO's using BAPI_PO_CREATE. I want to update the material document created for this PO during this BAPI. Is this possible and if yes how do I do it.

For reference - the material document no. is stored in EKBE as BELNR.

Note : I am creating the material document for this PO b4 creating the PO using MB1C. So now i need to update the PO with this created material documents.

Regards

Swanand

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Posted on Jan 17, 2005 at 01:19 PM

    Hi Swanand,

    if I remember correctly, it's possible to create POs automatically during goods receipt (by customizing...). If so, it's much better to change this PO later with BAPI_PO_CHANGE.

    I don't recommend to 'manually' link these documents afterwards.

    If you're already booking goods receipt by own program, switch order of these two steps. Then goods receipt with reference to PO is possible - if you run into performance problems, do both later offline (e.g. with storing info in Z-tables).

    Regards,

    Christian

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      hello christian,

      my requirement is as follows....

      I have a custom screen where in user enters some material and qty and i using custom tables calculate the value depending on conditions. Also simultaneously i do a goods receipt at this point using BAPI's.

      My next requirement is i shud use this calculated value in my PO and also link this above created material document to the PO. so i use the BAPI_PO_CREATE. I am thru the majority part except the linking of PO and material document since i want the standard interface of SAP wherein when i go in a PO i cana double click and view the material document.

      Regards

      Swanand

  • Posted on Jan 17, 2005 at 01:56 PM

    Hi Swanand,

    so your current process flow looks like this:

    a) data is entered

    b) calculation

    c) goods receipt (GR) like MB1C

    d) purchase order (PO)

    e) link them

    Do instead

    a) data is entered

    b) calculation

    c) PO

    d) GR with reference to PO like MB01

    Then you will have a correct link between your documents.

    Regards,

    Christian

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.