Hi Expert,
While im doing cost estimate with t.c ck11n , the following error is coming.
No itemization exists for material 92200 in plant 1001
i checked kp26 planing...........plan price is available.
i checked the BOM and ROUTING..........
But still im getting the error....
Please help me how to resolve....
in the error log im getting the following messages.
1) no object was costed.
2) Cost component split costed with value of zero
Has this been resolved now?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What is quantity in the BOM and price in KP26?
What is the costing lot size?
Increase the costing lot size and check.
Regards,
Divraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You need to add BOM validity dates. That should resolve your issues.
Also, the error 'Cost component split costed with value of zero' means that SAP encountered enough error messages and cannot calculate a product cost estimate. You will usually also see message CK 060 'Object not costed' at same time. So these messages are products of the error and not helpful in determining the error.
Hi,
Please check the setting in Material Origin in the Costing 1 view of the Material Master.
Regards,
Kiron Kumar T.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.