Not able to close project:

While closing a level 1 WBS, we are getting error message "Incoming order value not settled in full"

However for this project, All WBS below level-1 are closed and for level 1 WBS, no operative indicator is selected.

Not billing/ Planning or account assigned.

Also there is no order attached to this WBS element as wbs element is not a billing element.

Strange thing is now billing element indicator is gryed out.

So we could even not carryout CJA2/ KKA2 as this is not a billing element.

Also we could not reverse CJA2 as system gives error that WBS is non billing element. and we could not set it as it is gryed out,

CJI3 shows balance zero.

Also WBS settlement parameter we could not bring in edit mode so that we could change those.

Please assist how we could remove this error and close the WBS.

regards, madhu

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jul 18, 2011 at 01:13 PM

    Hi Madhu,

    Try CJEN. It may solve the issue.

    Warm regards,

    Srinivas Potluri

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.