Hi,

We have a WBS element at level 4 in a project. PRPS also shows the level as 4 but structure reports CN41N or cost/budget related S_ALR reports show that WBS at level 3. There seems to an inconsistency, can anyone advise how this inconsistency be corrected.

Thanks in advance.

Regards,

Mohammed T Haque

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jul 18, 2011 at 10:52 AM

    Hi,

    run CJEN transaction for reconstruct project info database for your project definition & then check.

    Regards,

    Sandeep

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Sreekanth,

      Thanks for the reply. I have checked the profile used in the report as well as filters etc,nothing other than standard.

      Raised with SAP as well, awaiting their response.

      Regards,

      Mohammed T Haque