Dear Gurus,

We have maintained strategy 40, requirement type VSF & mixed MRP indicator 1 alongwith consumption mode 3 in material master. Item category for sales order is having strategy 40 for. Still PIR are not getting consumed with sales order. Please provide the solution.

Regards,

SAP CONS

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jul 18, 2011 at 09:57 AM

    Hi,

    You do not need mixed MRP indicator to be set for stategy 40. Remove it to blank.

    Secondly make sure you have enough consumption period maintained so sales order can consume those PIRs'.

    Regards,

    Santosh Sarda

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 18, 2011 at 10:27 AM

    Please check

    MRP Type :- Should not be ND

    Procurement Type :- Should not be F

    Also check the planning file entry MD21.

    Thanks

    Kind regards

    A K

    Edited by: Ayaz Alam Khan on Jul 18, 2011 1:28 PM

    Edited by: Ayaz Alam Khan on Jul 18, 2011 1:48 PM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 18, 2011 at 10:46 AM

    Hi - you have maintained consumption mode 'forward'. Pls check if you have PIRs on future date to be consumed. Also check the 'forward consumption period'. The data entered is in days, and PIRs within that date will be consumed. So the forward consumption period should cover the earliest PIR in future date.

    Regards,

    Pradeep.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 18, 2011 at 10:55 AM

    Thanks

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 18, 2011 at 10:55 AM

    Dear,

    To control consumption, you maintain a consumption mode as well as a consumption period.

    what consumption period you are maintaining?

    Regards,

    Alok Tiwari

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.