Skip to Content
0

No schedule lines due for delivery up to the selected date error

Dec 15, 2016 at 06:43 PM

67

avatar image

Hi All,

My question is related to availability check. Sales Scenario at my client place is make to order. I have done the following settings,

Schedule line category: CP (in sales order)

Requirement type: KEV

requirement type assign to requirement type is: 045

Availability check in material master is: 02

Checking Rule: AE

all the above settings are also fetched in sales order

MRP type in material master is: PD

Strategy Group in MRP 4: Blank (even tried with 20)

based on above configuration when i try to do delivery system shows error "no schedule line due for delivery up to the selected date" though my date is same as of schedule line date and also material is available through 561 E initial upload. But when I change my schedule line category from CP to CN manually then I am able to create delivery.

Kindly suggest a solution to fix this as my schedule line should be CP.

Regards,

Vinay Singh

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

0 Answers