I am having one problem while maintaining shift sequence in work center. I have maintain all config settings in OP4A shift 1 shift 2 shift 3 but when I create work center and select shift sequence, it is only taking shift 1 and not all 3 shift for all 7 days.

Can anyone tell me the solution?

Thanks in advance.

Regards,

Max

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jul 18, 2011 at 09:52 AM

    Hi,

    You need to folow below procedue in op4A:

    1, Create a Group eg. standard pp 51

    2.Create a work break schedule and assign it to group.

    3. Define individual shifts wrt to groupo.

    4. Define Shift sequence using above shifts wrt to GROUP.

    5.Assign grouping in capacity header of work center.

    6.Now go to add interval option and create a new version of capcity which contains desired shift sequence from the shift group assigned.

    7. assign proper valid froma and valid to dates.

    8. In capacity header screena ssign the newly created capcity vesrion as active vesrion.

    This should resolve your problem.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.