Prerequisite statment for substitution

Hi friends,

Kindly help me for Prerequisite statement for below substitution requirement.

Substitution Requirement - In CJ01 or CJ02, when we assign or change the Person responsable at any WBS level and enter or save then this change need to effect for lower levee WBS elements.

So I am using " PRPS- VERNR field is substituted by RCJ_PRPSUP-VERNR" by selecting Filed Filed assignment.

This substitution need only for Engineering projects. That is the project which contain project profile PR001, PR002 and PR003.

I need the help for defining Prerequisite statement for the substitution.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jul 20, 2011 at 11:29 AM

    This will not work by substitution rule. can be achieved thru WBS BADI implementation -( WORKBREAKDOWN_UPDATE)

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.