on 07-18-2011 6:04 AM
Hi all,
I am creating PR for two materials and price is copying from material master, now my requirement is that PR price should copy into PO when i'm doing with reference to PR. Unfortunately another material price is not copying into PO.
Thax in advance
Hi
Always pr price getting from Material master and manual only.
You can't copy form PO
Laxman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to OMET - Here create a Function Authorisation key as ''01' and here under "General Parameters", activate "Adopt Po price" and maintain in User Master with Parameter ID 'EFB'.
In PR under "Valuation" Tab, you will get option of adopting PO Price as Gross or Net, select the appropriate option and then create PO w.r.t. PR.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.