We have got an unusual scenario in which we have to import/transport few Bex queries from Production to Development environment. I understand this is not a best practice, but any one suggest the way to implement the same.

Thanks,

Jay

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jul 16, 2011 at 06:54 AM

    Hi,

    You can do that but you need to have STMS path available to move the transports. Consult to your basis team.

    Regards,

    Durgesh.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 18, 2011 at 05:50 AM

    Hi,

    1. Collect the objects in a transport request in Production system. And after that, release it .

    2. Create "Transport copies" transport request form t code SE10/Se09.

    3. Insert the components of first Transport request ( created in step 1) into second transport request.

    4. now specify DEV system as the target system for 2nd TR and specify the client of DEV.

    5. Now release the second TR. And this TR will be there in DEV transport queue for getting import.

    Regards,

    Anil Kumar Sharma .P

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 18, 2011 at 07:37 AM

    Hi Jay,

    For every transport which moves a transport route is configured in transaction STMS (Transport Management System). Ideally it is Dev --> Qal --> Prod. Usually we do not have access to this transaction as Basis Team Configures this route. Check once in transaction STMS (if you have access) that whether the route Prod --> Dev is configured or not (i doubt it would be).

    In that case you can raise a request to Basis to configure this route for this exceptional case, if they agree then Transports can be moved via this new configured route.

    Regards

    Raj

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.