We are working for Cable manufacturing firm and wish to plan as per sales order priority in PP/DS. Presently we are using customized length based planning heuristics (which is customised form of SAP_PP_002) for creating planned orders.

We understand that the heuristics will plan as per requirement date of sales orders. But can we introduce sales priority. If we need to go for enhancement, please let us know the functional module which we need to use in the customized length based heuristics.

Our finished product is configurable material with make-to-order (strategy group u2013 26) and semi-finished product strategy is planning with final assembly (strategy group u2013 40). Accordingly, check modes are 047 and 050 respectively.

Regards,

S.Manjunath

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jul 14, 2011 at 07:25 PM

    S,

    ??? It is unclear what you mean when you say "plan as per sales order priority". Sales order priority is not usually managed during planning, but is instead normally managed during sales order availability checking, or during BackOrder Processing. The Check modes that you mentioned are relevant for availability checking, not normally relevant for planning.

    Anyhow, it doesn't really matter. As long as you can define in detail how you want your planning to be done, you can do it. Since you are already using a custom heuristic, you can modify your current heuristic to meet your new specs. Just change the custom code. Your developers should already know where to make the changes.

    Best Regards,

    DB49

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 19, 2011 at 01:42 PM

    Hi,

    here is a proposal:

    you first need to assign the priority to the sales order items in APO. That can be done via the LPRIO field in the sales order.

    Then you need to maintain that the sales order priority shall be inherited to the planned orders.

    [Determination of the Order Priority |http://help.sap.com/saphelp_scm700_ehp01/helpdata/EN/99/b1323dff83d228e10000000a114084/frameset.htm]

    Make the setting in your heuristic:

    Sort Procedure : 1. Order Priority 2. chronological order

    With that the system sorts the requirements by priority and time.

    BR Frank

    Add a comment
    10|10000 characters needed characters exceeded

    • Ok,

      you also want to filter for priorities.

      If you would set the Sort Procedure in the heuristic as I explained before to according to priority 1 and the desired availability date/time 2. The higher prioritized SOs would get planned first.

      To filter out all SO with priority 3 you need to implement

      Definition name /SAPAPO/RRP_PLANNING

      Definition short text BAdI for Procurement Planning Heuristics in PP

      Method

      PEGID_GET_IO Change the Receipts and Reqs After Reading from liveCache

      Parameter

      CT_IONODES

      delete all SO with PRIO_REQ = 3.

      BR Frank

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.