CTM--------No Planned Orders generated by CTM

Hello Folks,

I am working for a semiconductor company and this is a CTM implementation , the issue is CTM is not generating any Planned orders after its run. We are using Down binning concept in CTM. The CTM master data consistency check has no issues . Can any one help

Regards,

Aryan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jul 14, 2011 at 05:46 AM

    First check whether valid source of supply exists.

    First system chooses a valid SOS based on the Min and Max lot sze defined in the SOS.

    To create a order system refers to the Min and Max lot size defined in the Product master.

    Also check if there is sufficient cap to meet your demand.

    Thanks,

    nandha

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 15, 2011 at 11:07 AM

    Hi Aryan

    First ,check the CTM planning in 'Infinite Capacity mode'...

    Second ,check the Procurement type of the affected Product

    Third,check if the In-house-Product's PPM/PDS is read by CTM --i.e. the PPM/PDS is seen in MD Consistency check

    I hope this helps

    Best Regards

    Suresh