Hi experts,

We would like to have the price of the last Purchase Order each time we add a component to an activity (or to the unit costing of a cost activity).

Is this possible?

Is there any of the the options in the valuation variant in the Costing Variant for planned cost which suits our requirements?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

former_member203098
Active Contributor
0 Kudos

maintain the valuation variant strategy as price from purchasing info record. so that price would be updated from the latest PO.

;

regards,

fortian
Active Contributor
0 Kudos

What happens if I have more than one vendor?

I ask it because I've read this thread:

Thanks

former_member203098
Active Contributor
0 Kudos

in this case i don't see the feasibility, because say if you have 3 vendors supplying one material then how do you know which

vendor price is the best? how this comparison would happen in the system?

I think we have to go for user exist to map this. Discuss further with your MM/FI consultant.

regards,

fortian
Active Contributor
0 Kudos

The best vendor price would be the last one.