Production Order Cost to WBS Element control

Hi All,

We have a scenario where we create production orders in requirement to Projects, but when we create with assignment to WBS Element and do Raw material Goods Issue to Production Order, the actual cost of WBS is getting effected, how can I control this, I dont want the cost to affect the WBS at all, but want to create a production order with assignment to WBS? (or some reference).

Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    Jul 19, 2011 at 10:39 AM

    Dear RAMESH REDDY,

    Please check whether you have checked Append Plan update to category 20 in OPSV.

    If you have this tick, than this will automatically append the cost to WBSE Cost.

    if you want to create a production order with assignment to WBS than create this without having this indicator in OPSV.

    this will helpful for your requirement.

    Thanks

    Sunil

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Freids,

      Appending Planned cost will not be an issue here.

      Ramesh, hope you are creating a project structure in Plant B and Plant A is used for Production Manufaturing. In that case you should extend the material to both plants. When component was creaeted Project (plant A) and released, after MRP run system should create demand in Plant B. That means, Preq should be generated in Plant B and Planned Orde should be in Plant A.

      PReq will converted to PO (STPO - Stock transport Order) on Plant A and Planned order would be converted to Production. Here WBS element assignment will automatically default since PP order was created referencing planned order which was generated from MRP. With this you will see all your costs automatically reflecting on WBS element.

      I guess there could be problem in master data settings and MRP settings.You can check with your MM team for MRP settings and master master data settings for both plants.

      Regards,

      PSR

      Edited by: PSR on Jul 19, 2011 11:07 PM

  • Jul 12, 2011 at 11:16 AM

    are you using valuated project stock or non-valuated project stock