I have a material assigned to a quota arrangement usage in material master - MRP 2 View.
Source list maintained for the material/plant with 2 vendor codes and both releveant for MRP '1'
Quota arrangement maintained with proper validity periods.
But when i generate purchase requisitions via MRP, the source assignemnt is not happening. MRO generates PRs but the source of supply is blank. I have to assign the source either by ME57 or via 'assign source' tab in PR item details.
I have maintained EVO parameter in my user id also.
Not sure what I have missed. Please help!
Regards
Greg
Hi,
Please check following also -
1) Whether the vendor is not blocked for purchasing
2) If QM is activated & Delivery Release is required for the material, then check whether the Quality Info Record is maintained & the vendor is released for puruchase.
3) The scheduled delivery dates are lying inside the validity period of the Quota Arrangement & Source List
Regards,
Prasahnt Kolhatkar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prashant,
Vendor is not blocked/flagged for deletion & QI record available for the combination.
Delivery dates in the PR are within the quota and source list validity.
Also I am able to determine the sources via ME57 or 'assign source of supply' in PR item details. Only its not being picked up during the MRP run while generating requisitions.
Regards.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.