Hi Guruz,

I have a material assigned to a quota arrangement usage in material master - MRP 2 View.

Source list maintained for the material/plant with 2 vendor codes and both releveant for MRP '1'

Quota arrangement maintained with proper validity periods.

But when i generate purchase requisitions via MRP, the source assignemnt is not happening. MRO generates PRs but the source of supply is blank. I have to assign the source either by ME57 or via 'assign source' tab in PR item details.

I have maintained EVO parameter in my user id also.

Not sure what I have missed. Please help!

Regards

Greg

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please check following also -

1) Whether the vendor is not blocked for purchasing

2) If QM is activated & Delivery Release is required for the material, then check whether the Quality Info Record is maintained & the vendor is released for puruchase.

3) The scheduled delivery dates are lying inside the validity period of the Quota Arrangement & Source List

Regards,

Prasahnt Kolhatkar

former_member529134
Active Contributor
0 Kudos

Hi Prashant,

Vendor is not blocked/flagged for deletion & QI record available for the combination.

Delivery dates in the PR are within the quota and source list validity.

Also I am able to determine the sources via ME57 or 'assign source of supply' in PR item details. Only its not being picked up during the MRP run while generating requisitions.

Regards.

Former Member
0 Kudos

Hi,

Cross check.

As u have mentioned below,

Source list maintained for the material/plant with 2 vendor codes and both releveant for MRP '1'

Since u have maintained two vendor , did u fix any vendor in source list.

System will propose the vendor which is fixed for the particular validity period.

former_member529134
Active Contributor
0 Kudos

Hi ,

The problem was with the master data. The quota usage assigned in the material master was not relevant for MRP. The issue has been fixed.

Thnx.

Regards