Regarding Milestone Confirmations

14 Views

Dear Friends ,

I need few inputs regarding milestone cofirmation.

i have defined an new control key via transaction OP67 with Confirmation Value 1 ( mIlestONE confirmation).

Now suppose if one of my operation is having 5 phases , where do i need to assign this Control key , whether to last Phase of the operation or only to operation..? Also let me know after confirmattion , whether we can find the preceeding opeartions ,

in order confirmation screen . Or it will automatically get disappeaered as usual in-casre of stepwise Confirmation..?

Thanks in advance.