SAP Travel Management Integration with Time Management

Hello Gurus,

Need some assistance with Travel integration with Time Management.

Scenario.

Punch in Punch out system at the client so when the employee is traveling or when he enters the Trip Request, after approval the attendance should be counted.

Is there a config step for the same or a BADI needs to be implemented in this scenario ?

Regards,

BLITZZ

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jul 11, 2011 at 08:48 AM

    A direct update of time infotypes is not possible. You can however switch on the integration in view V_T702N_A. With add. user parameter START_CATS = X you have the possibility to jump to CAT2 to record the time. For the update of the infotypes you have to follow the subsequent steps in time management.