Report for actual cost of WBS, Profit center wise

Hi Experts,

Do we have any standard report that gives the actual cost of WBS/Project with Profit center wise.

Thanks,

Krishna

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Jul 07, 2011 at 09:22 PM

    Krishna,

    You can use the standard structure overview report (CN41) and from the choose fields option bring in the PC.

    Regards

    Sreekanth

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 08, 2011 at 03:52 AM

    Hi,

    YOu can use CJI3

    On CJIE GO to Dinamic selection -> expand Org Unit definition & double click on Prof.Cnt so that it appeasrs on creen.

    regards,

    SL

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 08, 2011 at 10:54 AM

    Hi Krishna,

    Open S_ALR_87013564 report and click on "Dynamic Selection" push button which is there just next to "Execute" push button or press (Shift+F4) then drill down "Org. units definition" and then double click on Profit Center and give profit center in the respective field.

    Hope this suffices the requirement.

    Thanks,

    Krishna Singh

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 09, 2011 at 08:39 AM

    Hi,

    If you are using New G/L , then transaction S_E38_98000088 - "Profit Center Group: Plan/Actual/Variance" would be helpful. In this report, you can drilldown to line items where profit center and WBS will be visible in one report. After analyzing the report, you can repost the line items with correct profit center.

    Hope this helps.

    Srinivas Potluri

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Gujju K

      Hi Krishna,

      Kindly have a look at KE5Z, actual line item report and sort based of the profit center and WBS element. Later you can repost the line items.

      Hope this helps.