Hi Anyone tried with an addional application server only with BG work processes ? . This will be my fifth new SAP application server

rdisp/wp_no_btc = 30

rdisp/wp_no_dia=0

rdisp/wp_no_vb=0

rdisp/wp_no_vb2=0

rdisp/wp_no_enq=0

rdisp/wp_no_spo=0

SAP recommends Note 39412 - How many work processes should be configured?

So each of our application servers have combination of DIA,BTC,

VB2,VB,SPO processes

There is no SAP note specifies that you can remove all the BTC work

processes from all application servers and configure one powerful serverwith lots of BTC processes.

I want to allocate one application server exclusively for BTC and all other application servers for DIA,VB,VB2,SPO,ENQ

I want to make rdisp/wp_no_btc=0 in all application servers. and create a new powerful application server with only rdisp/wp_no_btc=30.

has anyone tried like this?