Skip to Content
0
Former Member
Jul 07, 2011 at 06:44 AM

Budget Managed at Different WBS Elements

16 Views

Hi

I have a scenario where there are 2 WBS elements at 2nd level-one for material procurement and the other for the real construction work involving services etc.

I have a separate budget for material and a separate budget for construction involving servies and other miscellaneous works.As such I procure against the activities under material WBSE-in this process at the time of GR the budget is used.now when i transfer/issue the material to the other WBS then the system consumes budget from that WBS while in reality I never budgeted the WBSE for materials.And then I need to increase the construction WBS element budget.

This is where my problem is.I do not wish to get the budget checked while issuing the materials to the other WBS element and also the budget for the material WBS element should not be increased when materials are issued to the other WBS element.

Any suggestions?

Thanks and Regards