Dear PP Guru's,

We are in discrete manufacturing, there are several operations having capacity requirements say 24 hours .

But in actual we do not perform such operations at a go. We carry out operation in partial lots of operation qty. say each lot requires 4 hrs & there are 6 lots. Say for each lot operation is perforemed on alternate day.

My query is how we can split the capacity requirement of (single) operation in to six (lots) so that we can schedule each lots on alternate day. Currently we schedule capacity in CM31 where the order is shown in single block of 24 hrs.

Please suggest how to split the operation qty. Any configuration required to do so?.