on 12-15-2016 12:53 PM
Dear experts,
in the repetive manufacturing planning table (PP-REM) there is the possibility to display lines with minimum and maximum number personnel needed. (SAP help "Capacity Planning Using Personnel in the Planning Table")
I followed the instructions of the SAP help (setting in customizing and inserting number of personnel in routing; field PLPO-ANZMA) but I do not get a result in my planning table. The lines with min/max no. of personnel are not displayed.
I have searched the Internet as well as the SCN but could not find any hints where I can check what is wrong. Can you help me what to check?
Thank you in advance.
Kind regards,
A. Neuparth