Validate project stock indicator

Former Member
0 Kudos

The field PROJ-BESTA has either X or nothing as a value. I would like to check if project stock is Valuated or non-valuated.

Does it mean a user exit?

What is the second table to check Valuated vs Non-valuated stock for Project definition?

Thank you

Accepted Solutions (1)

Accepted Solutions (1)

anuradha_majumdar
Active Participant
0 Kudos

Check the field PROJ-KZBWS. It should be M for Valuated stock.

Regards,

Anuradha

Answers (1)

Answers (1)

stheurkar
Active Contributor
0 Kudos

Hi,

Try using Table MSSQ with field KZBWS (Valuation)

Regards,

Sandeep

Former Member
0 Kudos

Hi Sandeep,

The table mentioned has a primary key of material number and WBS-elements.

Valuated stock radio-button is part of Project Definition master record, that can exist without a single WBS-element.

So, I am afraid it is not the best way for potential solution...

Thank you.