on 07-05-2011 3:02 PM
Hi All,
My question is :
Once we have configured the ABAP-Stack of a dual-stack system into the transport domain through CTS, so can we now move the JAVA-based objects as well or we need to do something else also.
If so, what is that?
Regards
Hi Chilbul,
Your question is pretty vague. As per it, we don't know if you have actually carried out all the steps of CTS+ configuration prior to including the abap stack in transport routes or not.
If you have already completed CTS+ configuration and this was the last step you did, then your java developers should be able to include their objects in a transport request.
However, if you haven't done the CTS+ configuration yet, then please do that. For reference, these are some documents that should help you:
CTS+ config for dual stack systems -->
Other helpful guides:
/people/dolores.correa/blog/2009/06/05/cts-configuration-in-solution-manager-70-ehp1
http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/e0249083-c0ab-2a10-78b8-b7a7854b1070
Regards,
Shitij
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello chilbul
Once the CTS+ configuration is done you should be able to move Java objects using STMS like you move ABAP.
That is the whole purpose of CTS+.
Regards
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.