Process chain next step not triggering after making previous step green

Dec 15, 2016 at 12:09 PM

87

avatar image
Former Member

Hi all,

The process chain consists of a start step, an ABAP step and clear tables step.

The ABAP step had got cancelled and hence I made it green forcefully through RSPC_PROCESS_FINISH. Now the next step i.e clear tables step of the chain is not triggering and the overall status of the process chain is yellow. There is no option of "displaying messages" for this step to make it run forcefully. When checked in SM50 there is no background job running. There is a green line between ABAP step and Clear tables step.

Please suggest me on how to run this step.