Hi All.

I have one scenario in my current project where client does not want to use Key X he want to change the the key E to F or F to E as and when required.

Scenario.....

Procurment key F is maintained in some material A.

For this material A - Pur Req X000000001 exist now how to change the key to E for future requirements.

system does not allow to change the Key when Dep reqt exit for material A. Now if i am changing the Key in Table what will be the impact in my PR./PO.....

Also if the Key is E in material A and having one Prd order xxxx0002 now client want to procure it externally for future processing and he want to change the key F now what will the effect in my Prd Ord if i am changing the key from E to F.

Client Does not want to use Key --- X at any condition.

Kindly suggest is it better to change the Key using Table..................

Waiting for Earliest Reply.....

Thanks

Ravi

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Jul 04, 2011 at 08:03 AM

    Ravi, unfortunately not everything that a customer wants makes sense, like in your case.

    To me, it does not make any sense to keep on changing procuremt type often, from E to F or vice versa. That's what X is all about.

    Please tell us what is your customer's reasons for not using X!

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 04, 2011 at 08:59 AM

    Hi Ravi,

    You can not change procrument type fequently as you have to delete all the realted documents lik open PR/PO and close production orders which is not advisable in any case & no client would like to do that.

    Please tell the client that only solution given by SAP is Procrument type X sothat you can decide whether you want to produce inhouse or procure from outside.

    Regards,

    Sandesh.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 04, 2011 at 09:36 AM

    Ravi,

    As Mario rightly pointed, you should convince cleint about standard functionality in sAP and use X as procurement type .

    Otherwise use different material codes for external processing and inhouse production.

    Unfortunatily you dont have anyother solution in this case.

    Regards,

    Santosh Sarda

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.